Published on April 9, 2026
Construction Progress Update
Work on the Longhouse continues to move forward steadily, with several key milestones reached over the past month.
Site and Foundation Work
Construction within the building footprint has progressed in coordination with the Geotechnical Engineer, BC Hydro, and mechanical and electrical service providers. Insulation and dampproofing around the foundation and building perimeter have been completed. Mechanical and electrical services have been installed below the future floor slab, and backfilling is now complete in preparation for the upcoming concrete pour.
Structural Progress
The structural phase is advancing with engineered wood (glulam) post-and-beam installation and framed wall construction underway. The mechanical mezzanine floor and framing structure are now complete. Crews are also prefabricating wall and roof panels on site within a climate-controlled enclosure.
Civil and Site Coordination
Civil works specific to the Longhouse have been carried out in coordination with Sproat Lake Contracting, supporting site readiness and integration with underground services.
Next Steps
The project is preparing for the floor slab pour in the coming weeks. The kitchen component has also been initiated, with the contract in place and deposit submitted so fabrication and planning can begin.
Overall, the project continues to advance as planned, with strong coordination between contractors and consultants supporting steady progress into the next phase of construction.
Published on March 23, 2026
Site Walkthrough and Progress
This morning, I met with Kent Clark from Sproat Lake Contracting for a walkthrough of the Longhouse site to review progress.
Work is underway on what will become a welcoming entrance to the site. A gathering circle is being built at the front, wrapping around the entrance and creating a space for people to come together. From there, a bridge will lead into the main area, supported by massive logs, with a trail system running below and around the Longhouse. A steep dip in the trail will be raised to create a safer, more gradual incline.
The trail will also lead to an overlook facing the main part of the village, with views of the front beach and Elvis Mountain. Plans include picnic tables, wooden fencing, and thoughtful landscaping to make the space both functional and inviting.
Building Progress
Construction on the Longhouse itself continues to move forward. Foundation work has now reached slab level.
Crews are completing important groundwork, including insulation, underground services, and backfilling. These steps are necessary before the building structure begins to go up.
Behind the scenes, the main structural wood components are being prepared off-site. Early wall and roof panel assembly has begun on site, with additional prefabricated sections arriving in the coming weeks.
Quality and Safety
There have been some necessary setbacks along the way. The initial concrete footings did not meet required strength standards and were removed and redone to ensure the building is safe and built to last. The issue was identified early through careful oversight from Sproat Lake Contracting on site and was corrected at no cost to Ahousaht.
The Longhouse is being constructed as an earthquake-resistant structure, and care is being taken at every step to meet those standards.
Site Preparation and Vision
Site preparation includes clearing alders while keeping cedar and fir where possible. Blasting has taken place in Ahousahts rock quarry behind the lodge, video of one of the blasts will be in the slideshow below. These blasts can be felt throughout the village when they occur, all safety precautions were taken - community notices, road closures and drone footage before and during blasts. Gravel created was used on-site.
The long-term vision is to create a space that reflects both tradition and natural beauty, one that serves the community now and for future generations.
More updates will be shared as the project progresses.